Commercial Air Conditioning Solutions from SEMCO
SEMCO's ability to provide a highly professional service to our client enable solutions to be found to any complicated or diverse building problem, for example.
Case Study : Virgin Trains - Preston Station
This project consisted of the refurbishment of the ground floor and mezzanine level retail areas together with the second floor commercial area.
The building was the North Block located between platforms 3 and 4 within the centre of the station and in the middle of the rail tracks, so careful consideration of the problems likely to occur had to be resolved before installation commenced, especially as the building was listed.
The services installed included air conditioning, ventilation, heating, hot & cold water, soil & waste and electronic controls.
Any possible problems such as specific timed deliveries, working in an area which required 24 hour, 7 day public access and installing services within a listed building were overcome to enable the project to be successfully completed to the clients' satisfaction.
Case Study : Accor UK Hotels - Novotel Hammersmith
This project consisted of the design and installation of mechanical services for a new pavilion entrance at the hotel.
The services included air conditioning, utilising chilled water and LPHW heating fan coil units, fresh air and extract air ventilation and sprinkler installation.
Working to a complicated programme with a short time scale and constantly being aware of the occupancy of the hotel and having to work within tight noise restrictions, this project required both managerial and engineering expertise to achieve the aims and requirements of the client.
|